“Technically, we are ready. Only the contract remains. We are wrapping it up.”

That sounds reassuring. The hard work is done, the team has delivered and only formalities remain. Time to move on to the next topic.

A week later, we hear something similar. Comments have been exchanged, someone is due to respond and the final review is underway. It still sounds like the last stretch.

The problem starts when that “last stretch” never ends.

In one real status history, technical changes were ready while the contract continued moving between parties: comments, review, a meeting, waiting for the next version. A later entry still reported a missing document despite successive promised delivery dates. Each update, taken separately, described some activity. Read together, they showed that the condition required to launch the initiative remained unmet.

That is why status is worth recording.

Not so that a month later you can say, “But you promised.” So that you can notice now: “We keep doing things, but we still cannot move to the next stage. What is stopping us?”
Once a week. One record you can revisit

The basic rule is simple: once a week, the Head of Product and Product Owner review the initiatives and record the current state of each.

We do not need an elaborate reporting system. A shared document or table is enough. More important than the tool is giving every initiative its own place and dating each entry.

Append the new status. Do not replace the previous one.

That is the most important difference between an initiative’s history and a slide prepared for a meeting.

A slide shows how things look today. A history shows what has changed since last week. Or that nothing has changed, although each time we felt we were getting closer.

If we overwrite the “current status” field every